Smolensk nuclear power plant is a nuclear power station in Russia with 3 operating units totalling 3,000 MW gross. The site has 8 units on record in total.
Units
| Unit | Status | Type | Model | Gross MW | Online |
|---|---|---|---|---|---|
| Unit 1-1 | LWGR | RBMK-1000 | 1,000 | 1983 | |
| Unit 1-2 | LWGR | RBMK-1000 | 1,000 | 1985 | |
| Unit 1-3 | LWGR | RBMK-1000 | 1,000 | 1990 | |
| Unit 1-4 | Cancelled | LWGR | RBMK-1000 | 1,000 | - |
| Unit 2-1 | Pre-construction | PWR | VVER-TOI | 1,250 | 2033 |
| Unit 2-2 | Pre-construction | PWR | VVER-TOI | 1,250 | 2033 |
| Unit 2-3 | Cancelled (inferred) | PWR | VVER-TOI | 1,250 | - |
| Unit 2-4 | Cancelled (inferred) | PWR | VVER-TOI | 1,250 | - |
Unit by unit
Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.
Smolensk nuclear power plant 1-1
| Reactor type | Light water graphite reactor (LWGR) |
|---|---|
| Model | RBMK-1000 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | 925MW |
| Thermal output | 3,200MWt |
| Enrichment | 2–2.6% U-235 |
| NSSS vendor | Rosatom |
| Planned retirement | 2034planned, not actual |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 1 Oct 1975 |
|---|---|
| First criticality | 10 Sep 1982 |
| Grid connection | 9 Dec 1982 |
| Commercial operation | 30 Sep 1983 |
Smolensk nuclear power plant 1-2
| Reactor type | Light water graphite reactor (LWGR) |
|---|---|
| Model | RBMK-1000 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | 925MW |
| Thermal output | 3,200MWt |
| Enrichment | 2–2.6% U-235 |
| NSSS vendor | Rosatom |
| Planned retirement | 2034planned, not actual |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 1 Jun 1976 |
|---|---|
| First criticality | 9 Apr 1985 |
| Grid connection | 31 May 1985 |
| Commercial operation | 2 Jul 1985 |
Smolensk nuclear power plant 1-3
| Reactor type | Light water graphite reactor (LWGR) |
|---|---|
| Model | RBMK-1000 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | 925MW |
| Thermal output | 3,200MWt |
| Enrichment | 2–2.6% U-235 |
| NSSS vendor | Rosatom |
| Planned retirement | 2034planned, not actual |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 1 May 1984 |
|---|---|
| First criticality | 29 Dec 1989 |
| Grid connection | 17 Jan 1990 |
| Commercial operation | 12 Oct 1990 |
Smolensk nuclear power plant 1-4 Cancelled
| Reactor type | Light water graphite reactor (LWGR) |
|---|---|
| Model | RBMK-1000 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 2–2.6% U-235 |
| NSSS vendor | Rosatom |
| Cancelled | 1993 |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 1 Oct 1984 |
|---|
Smolensk nuclear power plant 2-1 Pre-construction
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-TOI |
| Size class | Large |
| Gross capacity | 1,250MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Commercial operation | 1 Jan 2033 |
|---|
Smolensk nuclear power plant 2-2 Pre-construction
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-TOI |
| Size class | Large |
| Gross capacity | 1,250MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Commercial operation | 1 Jan 2033 |
|---|
Smolensk nuclear power plant 2-3 Cancelled (inferred)
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-TOI |
| Size class | Large |
| Gross capacity | 1,250MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Cancelled | 2017 |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Milestones | no dates on record |
|---|
Smolensk nuclear power plant 2-4 Cancelled (inferred)
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-TOI |
| Size class | Large |
| Gross capacity | 1,250MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Cancelled | 2017 |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Milestones | no dates on record |
|---|
Smolensk nuclear power plant in context
By gross operating capacity Smolensk nuclear power plant is the 7th largest of 10 operating nuclear sites in Russia, holding 10% of the country's operating capacity, and ranks 40th of 172 worldwide.
Its operating units started up between 1983 and 1990; the median unit is 41.0 years old, older than the median of 37.5 in Russia.
The 3 units with both construction and grid dates on record took 5.7 to 9.0 years (median 7.2) from construction start to grid connection; the median across all reactors connected in the 1980s is 7.3 years.
The tracker lists a planned retirement year, a forecast and not a decision on record, for 3 operating units: Unit 1-1 (2034), Unit 1-2 (2034) and Unit 1-3 (2034).
Build time by unit
| Unit | Construction start | Grid connection | Years | Fleet median, same decade |
|---|---|---|---|---|
| Unit 1-1 | 1975 | 1982 | 7.2 | 7.3 (1980s) |
| Unit 1-2 | 1976 | 1985 | 9.0 | 7.3 (1980s) |
| Unit 1-3 | 1984 | 1990 | 5.7 | 8.0 (1990s) |
How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.
Earthquakes nearby
Loading the latest USGS check…
| Time (UTC) | Mag | Depth | Epicentre | Distance |
|---|
Magnitude 4.0 and above within 200 km of Smolensk nuclear power plant's listed coordinates, past 30 days. This is distance, not shaking: it says nothing about damage or any change in operation. Every plant.
| Location | Smolensk, Russia |
|---|---|
| Coordinates | 54.1658, 33.2358approximate |
| Elevation | not given: the position is only approximate |
| Setting | not given: the position is only approximate |
| Region | Eastern Europe |
| Units by status | Operating: 3 Cancelled: 3 Pre-construction: 2 |
| Owners | Rosatom |
|---|---|
| Operators | Rosenergoatom |
Put this plant on your own page: embed a card, or compare it with another plant.
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data