Rivne nuclear power plant
Rivne nuclear power plant is a nuclear power station in Ukraine with 4 operating units totalling 2,835 MW gross. The site has 11 units on record in total.
Units
| Unit | Status | Type | Model | Gross MW | Online |
|---|---|---|---|---|---|
| Unit 1 | PWR | VVER V-213 | 420 | 1981 | |
| Unit 2 | PWR | VVER V-213 | 415 | 1982 | |
| Unit 3 | PWR | VVER V-320 | 1,000 | 1987 | |
| Unit 4 | PWR | VVER V-320 | 1,000 | 2006 | |
| Unit 5 | Shelved (inferred) | PWR | AP-1000 | 1,250 | - |
| Unit SMR 1 | Shelved (inferred) | - | SMR-160 | 160 | - |
| Unit SMR 2 | Shelved (inferred) | - | SMR-160 | 160 | - |
| Unit SMR 3 | Shelved (inferred) | - | SMR-160 | 160 | - |
| Unit SMR 4 | Shelved (inferred) | - | SMR-160 | 160 | - |
| Unit SMR 5 | Shelved (inferred) | - | SMR-160 | 160 | - |
| Unit SMR 6 | Shelved (inferred) | - | SMR-160 | 160 | - |
Unit by unit
Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.
Rivne nuclear power plant 1
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER V-213 |
| Size class | Large |
| Gross capacity | 420MW |
| Net capacity | 381MW |
| Thermal output | 1,375MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | SE NNEGC "Energoatom"100% |
| Operator | SE NNEGC "Energoatom" |
| Construction start | 1 Aug 1973 |
|---|---|
| First criticality | 17 Dec 1980 |
| Grid connection | 22 Dec 1980 |
| Commercial operation | 22 Sep 1981 |
Rivne nuclear power plant 2
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER V-213 |
| Size class | Large |
| Gross capacity | 415MW |
| Net capacity | 376MW |
| Thermal output | 1,375MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | SE NNEGC "Energoatom"100% |
| Operator | SE NNEGC "Energoatom" |
| Construction start | 1 Oct 1973 |
|---|---|
| First criticality | 19 Dec 1981 |
| Grid connection | 22 Dec 1981 |
| Commercial operation | 29 Jul 1982 |
Rivne nuclear power plant 3
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER V-320 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | 950MW |
| Thermal output | 3,000MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | SE NNEGC "Energoatom"100% |
| Operator | SE NNEGC "Energoatom" |
| Construction start | 1 Feb 1980 |
|---|---|
| First criticality | 11 Nov 1986 |
| Grid connection | 21 Dec 1986 |
| Commercial operation | 16 May 1987 |
Rivne nuclear power plant 4
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER V-320 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | 950MW |
| Thermal output | 3,000MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | SE NNEGC "Energoatom"100% |
| Operator | SE NNEGC "Energoatom" |
| Construction start | 1 Aug 1986 |
|---|---|
| First criticality | 26 Sep 2004 |
| Grid connection | 10 Oct 2004 |
| Commercial operation | 6 Apr 2006 |
Rivne nuclear power plant 5 Shelved (inferred)
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | AP-1000 |
| Size class | Large |
| Gross capacity | 1,250MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Westinghouse Electric Company |
| Owner | SE NNEGC "Energoatom"100% |
| Operator | SE NNEGC "Energoatom" |
| Milestones | no dates on record |
|---|
Rivne nuclear power plant SMR 1 Shelved (inferred)
| Reactor type | small modular reactor |
|---|---|
| Model | SMR-300 |
| Size class | Small |
| Gross capacity | 160MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | not established |
| NSSS vendor | not on record |
| Owner | SE NNEGC "Energoatom"100% |
| Milestones | no dates on record |
|---|
Rivne nuclear power plant SMR 2 Shelved (inferred)
| Reactor type | small modular reactor |
|---|---|
| Model | SMR-300 |
| Size class | Small |
| Gross capacity | 160MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | not established |
| NSSS vendor | not on record |
| Owner | SE NNEGC "Energoatom"100% |
| Milestones | no dates on record |
|---|
Rivne nuclear power plant SMR 3 Shelved (inferred)
| Reactor type | small modular reactor |
|---|---|
| Model | SMR-300 |
| Size class | Small |
| Gross capacity | 160MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | not established |
| NSSS vendor | not on record |
| Owner | SE NNEGC "Energoatom"100% |
| Milestones | no dates on record |
|---|
Rivne nuclear power plant SMR 4 Shelved (inferred)
| Reactor type | small modular reactor |
|---|---|
| Model | SMR-300 |
| Size class | Small |
| Gross capacity | 160MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | not established |
| NSSS vendor | not on record |
| Owner | SE NNEGC "Energoatom"100% |
| Milestones | no dates on record |
|---|
Rivne nuclear power plant SMR 5 Shelved (inferred)
| Reactor type | small modular reactor |
|---|---|
| Model | SMR-300 |
| Size class | Small |
| Gross capacity | 160MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | not established |
| NSSS vendor | not on record |
| Owner | SE NNEGC "Energoatom"100% |
| Milestones | no dates on record |
|---|
Rivne nuclear power plant SMR 6 Shelved (inferred)
| Reactor type | small modular reactor |
|---|---|
| Model | SMR-300 |
| Size class | Small |
| Gross capacity | 160MW |
| Net capacity | not disclosed |
| Thermal output | not disclosed |
| Enrichment | not established |
| NSSS vendor | not on record |
| Owner | SE NNEGC "Energoatom"100% |
| Milestones | no dates on record |
|---|
Rivne nuclear power plant in context
By gross operating capacity Rivne nuclear power plant is the 3rd largest of 4 operating nuclear sites in Ukraine, holding 20% of the country's operating capacity, and ranks 44th of 172 worldwide.
Its operating units started up between 1981 and 2006; the median unit is 41.5 years old, older than the median of 39.0 in Ukraine.
The 4 units with both construction and grid dates on record took 6.9 to 18.2 years (median 7.8) from construction start to grid connection; the median across all reactors connected in the 1980s is 7.3 years.
The nearest other tracked nuclear sites are Khmelnitski nuclear power plant (125 km).
2 operating units are rated differently now from their design net capacities: Unit 1 +5.5% and Unit 2 -2.1%.
Build time by unit
| Unit | Construction start | Grid connection | Years | Fleet median, same decade |
|---|---|---|---|---|
| Unit 1 | 1973 | 1980 | 7.4 | 7.3 (1980s) |
| Unit 2 | 1973 | 1981 | 8.2 | 7.3 (1980s) |
| Unit 3 | 1980 | 1986 | 6.9 | 7.3 (1980s) |
| Unit 4 | 1986 | 2004 | 18.2 | 6.8 (2000s) |
Nearest tracked nuclear sites
| Site | Country | Distance | Operating GW gross |
|---|---|---|---|
| Khmelnitski nuclear power plant | Ukraine | 125 km | 2.0 |
How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.
Earthquakes nearby
Loading the latest USGS check…
| Time (UTC) | Mag | Depth | Epicentre | Distance |
|---|
Magnitude 4.0 and above within 200 km of Rivne nuclear power plant's listed coordinates, past 30 days. This is distance, not shaking: it says nothing about damage or any change in operation. Every plant.
| Location | Rivnenska, Ukraine |
|---|---|
| Coordinates | 51.3245, 25.8974 |
| Elevation | about 190 mabove sea level |
| Setting | About 520 km from the sea |
| Region | Eastern Europe |
| Units by status | Operating: 4 Shelved: 7 |
Elevation is read at the listed coordinates from a 30 m terrain model (SRTM 30 m). Two independent models differ by a median of 6 m across our plants and by up to about 40 m on steep or coastal ground, and a point on a shoreline can read as sea level. Distance to the water is measured to a generalised 1:10 million coastline, so a few kilometres or less is not resolved. This is context, not a design-basis or flood-risk figure.
| Owners | SE NNEGC "Energoatom" |
|---|---|
| Operators | SE NNEGC "Energoatom" |
Put this plant on your own page: embed a card, or compare it with another plant.
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data