Trawsfynydd nuclear power plant

Trawsfynydd nuclear power plant is a nuclear site in United Kingdom with 2 units on record. None is currently operating.

Operating1Pre-construction1Retired4circle area ∝ site capacitydashed = approximate position Coastlines, borders and lakes: Natural Earth (1:10 million, public domain), which is generalised, so a coastal plant can sit a couple of kilometres off its true shoreline. Site positions: Global Nuclear Power Tracker.
Units on record
2
Operating
0
Operating capacity
not disclosed

Units

UnitStatusTypeModelGross MWOnline
Unit 1 Retired GCR MAGNOX 235 1965
Unit 2 Retired GCR MAGNOX 235 1965

Unit by unit

Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.

Trawsfynydd nuclear power plant 1 Retired

Reactor typeGas-cooled reactor (GCR)
ModelMAGNOX
Size classSmall
Gross capacity235MW
Net capacity195MW
Thermal output850MWt
EnrichmentNatural uranium to 2.5–3.5% U-235no enrichment required
NSSS vendornot on record
OwnerNuclear Decommissioning Authority (United Kingdom)100%
OperatorMagnox
Construction start1 Jul 1959
First criticality1 Sep 1964
Grid connection14 Jan 1965
Commercial operation24 Mar 1965
Permanent shutdown6 Feb 1991

Trawsfynydd nuclear power plant 2 Retired

Reactor typeGas-cooled reactor (GCR)
ModelMAGNOX
Size classSmall
Gross capacity235MW
Net capacity195MW
Thermal output850MWt
EnrichmentNatural uranium to 2.5–3.5% U-235no enrichment required
NSSS vendornot on record
OwnerNuclear Decommissioning Authority (United Kingdom)100%
OperatorMagnox
Construction start1 Jul 1959
First criticality1 Dec 1964
Grid connection2 Feb 1965
Commercial operation24 Mar 1965
Permanent shutdown4 Feb 1991

Trawsfynydd nuclear power plant in context

The 2 units with both construction and grid dates on record took 5.5 to 5.6 years (median 5.6) from construction start to grid connection; the median across all reactors connected in the 1960s is 5.0 years.

The nearest other tracked nuclear sites are Heysham nuclear power plant (141 km), Hinkley Point nuclear power plant (199 km) and Hartlepool nuclear power plant (263 km).

Build time by unit

UnitConstruction startGrid connectionYearsFleet median, same decade
Unit 1195919655.55.0 (1960s)
Unit 2195919655.65.0 (1960s)

Nearest tracked nuclear sites

How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.

Site detail
LocationWales, United Kingdom
Coordinates52.9252, -3.9474
Elevationabout 200 mabove sea level
Setting7.9 km from the sea
RegionNorthern Europe
Units by status
Retired: 2

Elevation is read at the listed coordinates from a 30 m terrain model (SRTM 30 m). Two independent models differ by a median of 6 m across our plants and by up to about 40 m on steep or coastal ground, and a point on a shoreline can read as sea level. Distance to the water is measured to a generalised 1:10 million coastline, so a few kilometres or less is not resolved. This is context, not a design-basis or flood-risk figure.

Owners & operators
Owners
Nuclear Decommissioning Authority (United Kingdom)
Operators
Magnox

Put this plant on your own page: embed a card, or compare it with another plant.

Sources

How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data

Try

Searches every page: 1,823 reactors, 592 plants, 158 fuel chain facilities, companies, designs, accidents and notes.