Bundesgesellschaft für Endlagerung
Bundesgesellschaft für Endlagerung is a DEU company active in the nuclear fuel chain as repository.
The federal company responsible for German radioactive waste disposal, and for cleaning up the consequences of earlier attempts at it. It is building Konrad, sealing Morsleben with its contents in place, preparing to retrieve everything from Asse II at an estimated 4.7 billion euros, and running the search for a high-level site from a blank map after Gorleben was abandoned.
| Headquarters | Peine, Germany |
|---|---|
| Founded | 2016 |
| Ownership | state |
| Roles in the chain | repository |
Position in the chain
Facilities
| Facility | Stage | Country | Capacity / output | Status |
|---|---|---|---|---|
| Konrad | repository | DEU | 303,000m³ | construction |
| Asse II | repository | DEU | 47,000m³ | closed |
| Morsleben (ERAM) | repository | DEU | 37,000m³ | closed |
Bundesgesellschaft für Endlagerung in context
Bundesgesellschaft für Endlagerung has 3 facilities on record in 1 country (Germany): 0 operating and 1 planned, licensing or under construction.
How these are worked out: shares and ranks use the world totals cited in the table, and only named companies are ranked (unnamed or country-level entries in a source are not). A facility with no stated capacity is counted as a facility but adds nothing to a capacity figure. Vendor figures count operating units where this company is the recorded reactor vendor; ages count from the start-up year on record, and build times run from construction start to grid connection, as on the age and build-times pages.
Sources
- Bundesgesellschaft für Endlagerung, company source
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data