Ikata nuclear power plant 3

Operating Japan
Gross capacity
890MW

Ikata nuclear power plant 3 is a pressurised water reactor unit at Ikata nuclear power plant in Japan rated at 890 MW gross. It is operating. Commercial operation began 15 Dec 1994.

Specification
Reactor type Pressurised water reactor (PWR)
ModelM (3-loop)
Size classLarge
CoolantLight water
ModeratorLight water
Gross capacity890MW
Net capacity (reference)846MW
Net capacity (design)846MW
Thermal output2,660MWt
Typical enrichment3–5% U-235
Ownership & location
SiteIkata nuclear power plant
Unit3
CountryJapan
OwnerShikoku Electric Power Co Inc100%
OperatorShikoku Electric Power
Coordinates 33.4909, 132.3088
Fuel chain for this unit
Fuel form
Uranium dioxide pellets in zirconium-alloy cladding
Enrichment
3–5% U-235
Who makes this assembly
Upstream

Enriched fuel means this unit sits downstream of five conversion plants and four enrichment operators holding 88% of world capacity between the top three.

Fabricator capability is recorded against reactor type and model line, not against named units — utilities do not publish fuel contracts. See the fuel chain.

Timeline

  1. 1 Oct 1990Construction start
  2. 23 Feb 1994First criticality
  3. 29 Mar 1994Grid connection
  4. 15 Dec 1994Commercial operation

Other units at Ikata nuclear power plant

UnitStatusGross MW
Ikata nuclear power plant 1 Retired 566
Ikata nuclear power plant 2 Retired 566

Other M (3-loop) units

9 units worldwide share this model designation.

UnitCountryStatusGross MW
Mihama nuclear power plant 3 Japan Operating 826
Sendai nuclear power plant 1 Japan Operating 890
Sendai nuclear power plant 2 Japan Operating 890
Takahama nuclear power plant 1 Japan Operating 826
Takahama nuclear power plant 2 Japan Operating 826
Takahama nuclear power plant 3 Japan Operating 870
Takahama nuclear power plant 4 Japan Operating 870
Tomari nuclear power plant 3 Japan Under construction 912

Sources